File #: 2019-1972   
Type: Consent Calendar Item Status: Agenda Ready
File created: 12/30/2019 In control: Transportation and Public Works
On agenda: 2/4/2020 Final action:
Title: Second Amendment to the Agreement with Valley of the Moon Water District for Water System Improvements and Water Facility Adjustments for the Boyes Boulevard Bridge Replacement Project (County Project Number C01147)
Department or Agency Name(s): Transportation and Public Works
Attachments: 1. Summary Report, 2. Second Amendment, 3. Location Map

To: Board of Supervisors

Department or Agency Name(s): Transportation and Public Works

Staff Name and Phone Number: Johannes J. Hoevertsz 707-565-2231

Vote Requirement: Majority

Supervisorial District(s): First District

 

Title:

Title

Second Amendment to the Agreement with Valley of the Moon Water District for Water System Improvements and Water Facility Adjustments for the Boyes Boulevard Bridge Replacement Project (County Project Number C01147)

End

 

Recommended Action:

Recommended action

Authorize the Chair to execute the Second Amendment to the Agreement with the Valley of the Moon Water District, increasing Valley of the Moon Water District’s share of costs to $317,000 for water system improvements and water facility adjustments for the Boyes Boulevard Bridge Replacement Project (C01147). (First District)

end

 

Executive Summary:

The Boyes Boulevard Bridge Project is a mandatory seismic replacement project that is in the construction phase and consists of replacing Boyes Bridge with a new bridge and related roadway improvements. During utility relocation discussions, Valley of the Moon Water District (VOMWD) requested to have water system improvements and water facility adjustments included as work under the construction contract, and the Board of Supervisors approved an Agreement with the VOMWD on July 10, 2018 whereby Valley of the Moon would pay the County $253,200 for such improvements.

The Board awarded the construction contact for the Boyes Boulevard Replacement Project to Gordon Ball Inc. at the July 9, 2019 Board of Supervisors meeting. The cost of the water system improvements and water facility adjustments under the construction contract were higher than originally anticipated by the County and VOMWD at the time they executed the original Agreement. Based on the increased cost of construction, this Second Amendment to the Agreement raises VOMWD’s contribution for the water system improvements from $253,200 to $317,000.

 

Discussion:

The existing two-lane bridge on Boyes Boulevard over Sonoma Creek (Bridge Number 20C0262) has been found to be functionally obsolete. The Boyes Boulevard Bridge Replacement Project will include improvements to the roadway approaches and appurtenant facilities. The new replacement bridge will comply with current roadway, drainage and bridge standards to accommodate the 100-year storm event with freeboard as specified by the County. The Boyes Boulevard Bridge Replacement Project does not increase vehicular capacity but will provide a shoulder for bicycles and a 5-foot sidewalk for pedestrians.

The Boyes Boulevard Bridge Replacement Project improvements include adjustments and improvements to water facilities owned by the VOMWD, which are located within the right of way. Adjustments will be made to water valves and water meters, and improvements include water main replacement and associated water lateral and water appurtenance replacements.

On July 10, 2018, the Board approved a Utility Agreement with VOMWD for these water systems adjustments and improvements. VOMWD agreed to fund $253,200 of the necessary work, which included a 10% construction contingency and County project administration fees. After Caltrans review of the Utility Agreement the parties executed a First Amendment to the Agreement in December 2018.  The Amendment added required federal aid project language but did not affect the financial terms of the contract.

The Board awarded the construction contract for the entire Boyes Boulevard Bridge Replacement Project to Gordon Ball Inc. at the July 9, 2019 Board of Supervisors meeting. Due to increases in overall construction costs within the County, the price of the water system work under the contract with Gordon Ball, was higher than originally anticipated. The contracted amount for the required work is now budgeted to be $371,250. This Second Amendment increases VOMWD’s share of the water system work from $253,200 to $317,000. The County has agreed to pay the remaining $54,250 cost of various items of work associated with the water system improvements if necessary, while looking to reduce these costs through construction project management. Should unforeseen circumstances result in cost increases beyond the current estimates, those costs will be the responsibility of VOMWD.

The water system work will occur concurrently with the Boyes Boulevard Bridge Replacement Project and is anticipated to be completed by mid-2021.

 

Prior Board Actions:

8/6/2019: Board awarded the administration of the Boyes Boulevard Bridge Replacement construction contract to Ghirardelli Associates, Inc.

7/9/2019: Board awarded the Boyes Boulevard Bridge Replacement construction contract to Gordon Ball, Inc.

6/11/2019: Board approved Third Amendment to agreement with Moffatt and Nichol, extending the term of the agreement to December 2021 at no additional cost.

7/10/2018: Board approved agreement with VOMWD for water systems improvements.

4/4/2017: Board approved Second Amendment to agreement with Moffatt and Nichol for additional design services to design for VOMWD’s water system improvements and related design services during the construction phase.

9/1/2015: Board approved First Amendment to agreement with Moffatt and Nichol, extending the term of the agreement to June 2019 at no additional cost.

5/7/2013: Board approved agreement with Moffatt and Nichol for engineering design work for Boyes Bridge over Sonoma Creek.

 

Fiscal Summary

 Expenditures

FY 19-20 Adopted

FY20-21 Projected

FY 21-22 Projected

Budgeted Expenses

$185,625

$185,625

 

Additional Appropriation Requested

 

 

 

Total Expenditures

$185,625

$185,625

 

Funding Sources

 

 

 

General Fund/WA GF

 

 

 

State/Federal

 

 

 

Fees/Other (Utility Agreements)

$158,500

$158,500

 

Use of Fund Balance

$27,125

$27,125

 

Contingencies

 

 

 

Total Sources

$185,625

$185,625

 

 

Narrative Explanation of Fiscal Impacts:

This amendment increases VOMWD contribution to the project from $253,200 to $ 317,000 in funding. Remaining project costs will be funded with SB1 revenues.

 

Staffing Impacts:

 

 

 

Position Title (Payroll Classification)

Monthly Salary Range (A-I Step)

Additions (Number)

Deletions (Number)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Narrative Explanation of Staffing Impacts (If Required):

None.

 

Attachments:

Location Map

Second Amendment

 

Related Items “On File” with the Clerk of the Board:

Agreement and First Amendment between VOMWD and County of Sonoma.