Legislation Details

File #: 2022-0979   
Type: Consent Calendar Item Status: Passed
File created: 8/24/2022 In control: Transportation and Public Works
On agenda: 10/18/2022 Final action: 10/18/2022
Title: Approve Contract Change Order No. 5 for the 2021 Pavement Preservation Program
Department or Agency Name(s): Transportation and Public Works
Attachments: 1. Summary Report, 2. C21401- Contract Change Order 5

To: Board of Supervisors

Department or Agency Name(s): Transportation and Public Works

Staff Name and Phone Number: Johannes J. Hoevertsz, 707-565-2231

Vote Requirement: Majority

Supervisorial District(s): First, Second, Fourth and Fifth

 

Title:

Title

Approve Contract Change Order No. 5 for the 2021 Pavement Preservation Program

End

 

Recommended Action:

Recommended action

Approve a final contract change order of $268,200 to close out the construction contract with Ghilotti Bros Inc. for the 2021 Pavement Preservation Program (Contract C21401). (First, Second, Fourth and Fifth Districts

end

 

Executive Summary:

On May 18, 2021, the Board awarded a construction contract to Ghilotti Bros Inc. for the 2021 Pavement Preservation Program (PPP). The total value of the contract at the time of award was $14,947,418.25, which included a 15% contingency. Construction was successfully completed in early 2022 with the paving of nearly 27 miles of road.

The Department of Transportation and Public Works (TPW) is requesting that the Board approve a final Contract Change Order No. 5 in the amount of $268,200 for the project closeout of the 2021 PPP.

In accordance with Resolution No. 20-0092 and State law, TPW Director’s delegated authority for contract change orders is capped at $210,000.00 for this contract. The previous four contract change orders were under TPW’s delegated authority.  This final contract change order requires Board approval. 

 

Discussion:

On May 18, 2021, the Board awarded the 2021 PPP - Full-Depth Reclamation and Overlays construction contract to Ghilotti Bros Inc.  This contract included pavement treatment on 26.76 miles of County roads.

The contract work began in June 2021 and was completed in early 2022. A Notice of Completion was filed June 30, 2022.

There have been four previous contract change orders on this project, all within TPW Director’s delegated authority.  Below is a brief summary of the contract change orders to date:

CCO 1 - Drainage Modifications                                                                                    $  59,531

CCO 2 - South Fitch Mountain Viaduct Repairs                                          $208,028

CCO 3 - Miscellaneous Extra Work Bills                                                               $181,579

CCO 4 - Item Price Adjustments for Changed Quantities                     $(19,112)

This final Contract Change Order No. 5 is intended to close out the project.  Contract Change Order No 5 includes sewer manhole adjustments, water trucking and flagging costs.

The total amount paid to date to Ghilotti Bros is $13,145,562.51.

If approved, this final Contract Change Order for $268,200.00 will bring the final contract total to $13,413,762.51. The total 2021 PPP cost including this construction contract, professional service fees for design, environmental review, and construction management as well as labor costs for County staff will be approximately $15,787,340. General Fund contributions to the PPP in 2021 were $12,622,872 with the balance of the project funded by SB1. 

 

Strategic Plan:

This item directly supports the County’s Five-year Strategic Plan and is aligned with the following pillar, goal, and objective.

 

Pillar: Resilient Infrastructure

Goal: Goal 3: Continue to invest in critical road, bridge, bicycle, and pedestrian infrastructure.

Objective: Objective 1: Continue to maintain road segments, including designated turnouts where feasible, increase efforts on vegetation removal and drainage features, and improve pavement conditions in neighborhoods.

 

Prior Board Actions:

5/18/2021-                     Board Awards Construction Contract for 2021 PPP to Ghilotti Bros for $14,947,418.25

3/17/2020-                     Board Resolution 20-0092

5/21/2019-                     Board approved 2-year Pavement Preservation Program for 2020-21

 

Fiscal Summary

 Expenditures

FY 22-23 Adopted

FY23-24 Projected

FY 24-25 Projected

Budgeted Expenses

$268,200

 

 

Additional Appropriation Requested

 

 

 

Total Expenditures

$268,200

 

 

Funding Sources

 

 

 

General Fund/WA GF

$268,200

 

 

State/Federal

 

 

 

Fees/Other

 

 

 

Use of Fund Balance

 

 

 

Contingencies

 

 

 

Total Sources

$268,200

 

 

 

Narrative Explanation of Fiscal Impacts:

Appropriations for the change order requested in this Board Item were included in the FY 2022-23 Roads Capital Adopted Budget (11051-34010103). The PPP is funded through annual contributions from the General Fund approved by the Board of Supervisors, the Transit Occupancy Tax (Measure L), and allocations from the Road Maintenance and Rehabilitation Account (SB1).

 

Narrative Explanation of Staffing Impacts (If Required):

None

 

Attachments:

Change Order

 

Related Items “On File” with the Clerk of the Board:

None.