Legislation Details

File #: 2026-1061   
Type: Consent Calendar Item Status: Agenda Ready
File created: 9/17/2026 In control: Public Infrastructure
On agenda: 11/3/2026 Final action:
Title: State Route 116 Downtown Guerneville Complete Streets Maintenance Agreements with Caltrans
Department or Agency Name(s): Public Infrastructure
Attachments: 1. Summary Report, 2. Resolution, 3. DMA with Sonoma County.pdf, 4. PSMA with Sonoma County for Sr116 Guerneville.pdf

To: Board of Supervisors

Department or Agency Name(s): Sonoma County Public Infrastructure

Staff Name and Phone Number: Johannes J. Hoevertsz, 707-565-2550

Vote Requirement: Majority

Supervisorial District(s): Fifth

 

Title:

Title

State Route 116 Downtown Guerneville Complete Streets Maintenance Agreements with Caltrans

End

 

Recommended Action:

Recommended action

A)                     Adopt a Resolution approving the Delegated Maintenance Agreement and Project Specific Maintenance Agreement with the State of California Department of Transportation (Caltrans) for State Route 116 in downtown Guerneville between Brookside Lane and Old River Road.

B)                     Authorize the Director of Sonoma County Public Infrastructure to execute both agreements.

end

 

Executive Summary:

Sonoma County Public Infrastructure (SPI) requests that the Board approve two maintenance agreements with Caltrans for State Route 116 in downtown Guerneville, between Brookside Lane and Old River Road, and delegate authority to the Director of Public Infrastructure to execute both agreements.

The Delegated Maintenance Agreement (DMA) delegates responsibility for litter and debris maintenance to the County and provides the County reimbursement from Caltrans of actual and necessary costs up to $10,000 annually. The Project Specific Maintenance Agreement (PSMA) establishes the County maintenance responsibilities for specified complete streets features and enhancements within State right of way.

 

Discussion:

Caltrans served as the lead agency for a project to improve pedestrian accessibility and safety along State Route 116 in downtown Guerneville. The project extends from Brookside Lane to Old River Road and includes ADA-compliant sidewalk improvements, intersection bulb-outs, pedestrian lighting, and pedestrian hybrid beacons at the Mill Street and Church Street intersections.

The project improvements are nearing completion, but before construction can be finalized Caltrans and the County must enter into two agreements establishing ongoing maintenance responsibilities: a Delegated Maintenance Agreement (DMA) and a Project Specific Maintenance Agreement (PSMA).

The proposed DMA delegates responsibility to the County for litter and debris maintenance along   approximately 0.4 mile of State Route 116. Covered activities include debris and carcass pickup, sweeping, litter pickup, spill response, graffiti removal, and miscellaneous litter and debris maintenance. Caltrans will reimburse the County for actual and necessary costs incurred under the DMA, up to a maximum annual authorized expenditure of $10,000.

The proposed PSMA establishes ongoing maintenance responsibilities for the complete streets features and enhancements identified in Exhibit A of the agreement. Under the PSMA, the County will maintain specified ornamental streetlights and associated appurtenances, street furniture, bicycle racks, trash receptacles, flag pole sleeves, street trees, tree wells, planters, landscaping, and irrigation systems. The County would also be responsible for electricity costs for the ornamental streetlights.

Both agreements require maintenance activities performed within State right of way to comply with applicable State standards and contain applicable insurance and indemnification provisions. Approval of the agreements will formalize the respective ongoing maintenance responsibilities of Caltrans and the County and will allow Caltrans to complete and close out the construction phase of the State Route 116 improvement project.

SPI requests the Board adopt a resolution approving the proposed Delegated Maintenance Agreement and Project Specific Maintenance Agreement with the State of California Department of Transportation (Caltrans) for State Route 116 in downtown Guerneville between Brookside Lane and Old River Road and delegate authority to the Director of SPI to execute both agreements.

 

Strategic Plan:

 

This item directly supports the County’s Five-year Strategic Plan and is aligned with the following pillar, goal, and objective.

 

Pillar: Resilient Infrastructure

Goal: Goal 3: Continue to invest in critical road, bridge, bicycle, and pedestrian infrastructure.

Objective: Objective 3: Invest $5 million by 2024 on new pedestrian and bicycle facilities, and adopt maintenance guidelines on roads to consider bicyclists and pedestrians.

 

 

Racial Equity:

 

Was this item identified as an opportunity to apply the Racial Equity Toolkit?

No

 

 

Prior Board Actions:

6/15/2023 - Caltrans Cooperative Agreement State Route 116 ADA Sidewalks in Downtown Guerneville

 

 

 

 

 

 

 

 

 

 

 

 

Fiscal Summary

 Expenditures

FY26-27 Adopted

FY27-28 Projected

FY28-29 Projected

Budgeted Expenses

$15,000

$15,000

$15,000

Additional Appropriation Requested

 

 

 

Total Expenditures

$15,000

$15,000

$15,000

Funding Sources

 

 

 

General Fund/WA GF

 

 

 

State/Federal

$12,000

$12,000

$12,000

Fees/Other (Countywide Lighting)

$3,000

$3,000

$3,000

Use of Fund Balance

 

 

 

General Fund Contingencies

 

 

 

Total Sources

$15,000

$15,000

$15,000

 

Narrative Explanation of Fiscal Impacts:

Appropriations for the proposed Maintenance Agreements are included in the FY 2026-27 Road Maintenance (11051-34010102) and Countywide Lighting (15101-34090100) adopted budgets. Appropriations for future fiscal years will be included in future recommended annual budgets.

The proposed DMA is estimated to cost $10,000 annually and is reimbursable by Caltrans up to $10,000 per year.

Under the proposed PSMA, Countywide Lighting will fund maintenance of the ornamental streetlights and associated appurtenances, including electricity costs, at an estimated annual cost of $3,000. Roads will fund all remaining maintenance responsibilities, estimated at $2,000 annually, using traditional Road funding sources such as the Highway User Tax Account (HUTA) or Road Maintenance and Rehabilitation Account (SB1).

 

Narrative Explanation of Staffing Impacts (If Required):

None.

 

Attachments:

1. Resolution
2. Delegated Maintenance Agreement, Statement of Self Insurance, and Exhibit A
3. Project Specific Maintenance Agreement, Statement of Self Insurance, and Exhibit A

 

Related Items “On File” with the Clerk of the Board:

None.