File #: 2024-1071   
Type: Consent Calendar Item Status: Agenda Ready
File created: 9/4/2024 In control: Public Infrastructure
On agenda: 10/22/2024 Final action:
Title: Fourth Amendment to the Professional Services Agreement with TRC Engineers, Inc. for design of the Geysers Road Bridge over Frasier Creek Replacement Project.
Department or Agency Name(s): Public Infrastructure
Attachments: 1. Summary Report, 2. 4th Amendment, 3. Exhibit A_Amend 4 Frasier Creek Bridge_Scope+Fee

To: Board of Supervisors

Department or Agency Name(s): Sonoma County Public Infrastructure

Staff Name and Phone Number: Johannes J. Hoevertsz, 707-565-2550

Vote Requirement: Majority

Supervisorial District(s): Fourth

 

Title:

Title

Fourth Amendment to the Professional Services Agreement with TRC Engineers, Inc. for design of the Geysers Road Bridge over Frasier Creek Replacement Project.

End

 

Recommended Action:

Recommended action

Approve and authorize the Chair to execute a fourth amendment to the Professional Services Agreement with TRC Engineers, Inc. for additional design services in the amount of $266,069, related to the replacement of the Geysers Road Bridge over Frasier Creek (C11005) resulting in a contract not-to-exceed value of $1,081,040.

end

 

Executive Summary:

Sonoma County Public Infrastructure (SPI) requests Board approval of a fourth amendment to the Agreement with TRC Engineers, Inc. (Agreement) for engineering and design services and construction support related to replacement of the Geysers Road Bridge over Frasier Creek (C11005).

The proposed amendment will increase the contract amount by $266,069. No additional contingency is proposed. This amendment will allow TRC Engineers, Inc. to complete design and to provide bid and construction support to SPI for this project. If approved, the new not-to-exceed value of the contract will be $1,081,040.

 

Discussion:

The Geysers Road Bridge over Frasier Creek project will result in the construction of a new two-lane bridge on the same alignment as the existing, but functionally obsolete two-lane bridge. The new bridge will be designed to meet current design standards including improvements to roadway approaches and appurtenant facilities. As part of this project, the existing bridge will be removed after construction of the new bridge. The project does not increase vehicular traffic capacity; however, it will provide two traffic lanes with shoulders as required by applicable standards. Due to the low traffic volume on Geysers Road, pedestrians, bicycles, and vehicles will share the travel lanes and shoulders.

In 2014, SPI issued a Request for Qualifications for design services for the Geysers Road Over Frasier Creek Bridge Replacement Project (C11005). TRC was selected as the most qualified consultant to provide these services and the original Agreement was approved by the Board of Supervisors on October 7, 2014. TRC’s work includes civil engineering and design, geotechnical engineering, traffic studies, hydraulics and hydrology, environmental studies, public outreach, and construction support services. The Agreement was originally for an amount not to exceed $559,260 (including 10% contingency).

On December 13, 2016, the Board approved a first amendment to extend the term of the Agreement at no additional cost through December 31, 2021. 

On September 12, 2017, the Board approved a second amendment increasing the contract value by $16,387 to complete a required archeological survey report.

On December 7, 2021, the Board approved a third amendment increasing the contract value by $216,078 for additional design work associated with updated regulatory requirements and California bridge design standards. In addition, the third amendment extended the term through December 31, 2026. 

SPI is now recommending the Board approve a Fourth Amendment (“Amendment”) to the Agreement with TRC Engineers, Inc. (TRC) in order to complete the final design and to provide bid and construction support for the Geysers Road Bridge over Frasier Creek project (C11005). The Amendment will increase the total contract value by $266,069 for a new, total not to exceed cost of $1,081,040 (including $74,088 contingency). The term of the contract will not be affected by this amendment and will remain December 31, 2026.

The project is receiving Federal funds and must satisfy all requirements of the Federal Highway Bridge Program, including approval by Caltrans. On June 13, 2022, by Resolution No. 22-0246, the Board adopted a Mitigated Negative Declaration and Mitigation Monitoring Program and approved the project. The project is currently in the right-of-way phase. Construction is anticipated to begin in 2025.

 

Strategic Plan:

 

This item directly supports the County’s Five-year Strategic Plan and is aligned with the following pillar, goal, and objective.

 

Pillar: Resilient Infrastructure

Goal: Goal 3: Continue to invest in critical road, bridge, bicycle, and pedestrian infrastructure.

Objective: Objective 4: Identify and retrofit bridges in County that are at high risk for damage during earthquakes.

 

Racial Equity:

 

Was this item identified as an opportunity to apply the Racial Equity Toolkit?

No

 

 

Prior Board Actions:

6/13/22 - Item 29: Resolution Adopting a Mitigated Negative Declaration and Mitigation Monitoring Program and Approving the Geysers Road Bridge over Frasier Creek Project

12/7/21 - Item 37: Third Amendment to the Agreement with TRC Engineers, Inc. for design of the Geysers Road Bridge over Frasier Creek Replacement Project

9/12/17 - Item 28: Second Amendment to the Agreement with TRC Engineers, Inc. for design of the Geysers Road Bridge over Frasier Creek Replacement Project

12/13/16 -Item 55: First Amendment to the Agreement with TRC Engineers, Inc. for design of the Geysers Road Bridge over Frasier Creek Replacement Project

10/7/14 - Item 37: Geysers Road over Frasier Creek Replacement Bridge Design Contract Award to TRC Engineers, Inc.

 

Fiscal Summary

 Expenditures

FY24-25 Adopted

FY25-26 Projected

FY26-27 Projected

Budgeted Expenses

$121,542

$144,527

 

Additional Appropriation Requested

 

 

 

Total Expenditures

 

 

 

Funding Sources

 

 

 

General Fund/WA GF

 

 

 

State/Federal

$121,542

$144,527

 

Fees/Other

 

 

 

Use of Fund Balance

 

 

 

General Fund Contingencies

 

 

 

Total Sources

$121,542

$144,527

 

 

Narrative Explanation of Fiscal Impacts:

Appropriations associated with this contract amendment are included in the FY 2024-25 Roads Capital (11051-34010103) budget. Future expenses will be included in the FY 2025-26 Roads Capital (11051-34010103) Recommended budget. These expenditures are reimbursable through the Federal Highway Bridge Program (HBP).

 

Narrative Explanation of Staffing Impacts (If Required):

N/A

 

Attachments:

Fourth Amendment, Exhibit A

 

Related Items “On File” with the Clerk of the Board:

Original Contract Agreement

First Amendment - No cost contract extension through 2021

Second Amendment - Added cost for preliminary cultural review

Third Amendment - Added cost and extended contract through 2026