Skip to main content
File #: 2025-0667   
Type: Consent Calendar Item Status: Agenda Ready
File created: 5/22/2025 In control: Public Infrastructure
On agenda: 7/8/2025 Final action:
Title: Second Amendment - Engineering Services for Design of Leachate and Potable Water Storage Tank Replacements Project
Department or Agency Name(s): Public Infrastructure
Attachments: 1. Summary Report, 2. Second Amendment - GHD, 3. Exhibit A-2 - Scope of Services, 4. Exhibit B-2 - Cost of Services, 5. Exhibit C-1 - Schedule of Rates

To: Board of Supervisors

Department or Agency Name(s): Sonoma County Public Infrastructure

Staff Name and Phone Number: Johannes J. Hoevertsz, 707-565-2550

Vote Requirement: Majority

Supervisorial District(s): First, Second, Fourth, Fifth

 

Title:

Title

Second Amendment - Engineering Services for Design of Leachate and Potable Water Storage Tank Replacements Project

End

 

Recommended Action:

Recommended action

Authorize the Chair to execute a Second Amendment to the Professional Services Agreement with GHD, Inc. for engineering services related to the Leachate and Potable Water Storage Tanks Replacement Project, expanding the scope of work and increasing the total contract budget by $78,164, for a new not-to-exceed amount of $808,134.

end

 

Executive Summary:

Sonoma County Public Infrastructure is requesting authorization to execute a Second Amendment to an agreement with GHD, Inc. expanding the scope of work and increasing the total contract budget by $78,164, for a new not-to-exceed amount of $808,134.  The expanded scope of work includes additional engineering design, document preparation, bid assistance, and construction support services.

 

Discussion:

Background

On July 20, 2021, the Board approved a $651,775 contract with GHD, Inc for engineering services for the design of two new steel bolted leachate tanks at three of the County’s closed landfills (six total tanks), as well as the design of potable water storage tanks for the CSA #41 Fitch Mountain water system for a total not-to-exceed $651,775.

On May 24, 2022, the Board approved a first Amendment to the Agreement for additional design and geotechnical investigative work associated with the construction phase of the project, which increased the total, not-to-exceed contract amount to $729,970. A one-year extension was executed in 2024, extending the initial term of the agreement through July 20, 2025.

As part of the standard project delivery process, the initial construction bid did not result in an award, requiring the project to be re-bid. This triggered the need for revised cost estimates, updated technical specifications, and additional bid-phase support from GHD. These updates were necessary to reflect changes in material pricing, including tariff-related fluctuations that impacted the cost of steel and other supplies since the original design work was completed.

The project is now in active construction, with six 200,000-gallon welded steel tanks being installed across three geographically separated sites. The additional work addressed by this Second Amendment includes enhanced construction support, inspection services, and as-needed engineering responses to field conditions - ensuring continuity and quality during this complex installation phase. This amendment increases the not-to-exceed amount to $808,134.

The additional scope of work includes: 

Task 5 Engineering Design and Bid Documents Preparation

Revisions to design documents and specifications required for rebidding. This includes updating the leachate and water tank specifications as well as revising the engineer’s cost estimates for both systems.

Task 6 - Bid Assistance

Required an increased budget due to a second round of responses to bidder questions and the preparation of additional addenda.

Task 7 - Construction Support Services

Expands construction support services to include rebar special inspections and geotechnical observation and testing. GHD has performed tank foundation inspection, compaction testing, and concrete inspection and reporting for the Guerneville site; drilled piers inspection, concrete inspection, key and bench inspection, and reporting for the Roblar site; and tank foundation inspection and reporting for the Sonoma site. Rebar inspections and documentation were provided for all three locations: Guerneville, Roblar, and Sonoma.

Task 9 - Additional Construction Support Services

A new Task 9 was created for as-needed construction support to address submittal reviews and responses of Request For Information (RFIs), and other construction-phase support activities as needed.

Tasks 5, 6, and 7 are adjusted to reflect additional work as revised lump sum amounts, while Task 9 will be billed on a time-and-material basis, providing a flexible mechanism to address emerging field conditions throughout the construction phase.

The additional scope and unforeseen conditions encountered since the First Amendment including re-bidding efforts, updated specifications, enhanced construction support services, and expanded inspection requirements necessitate a Second Amendment to the agreement with GHD, Inc. The Amendment will support these critical services and ensure successful delivery of the Leachate and Potable Water Storage Tanks Replacement Project.

Staff recommends that the Board authorize the Chair to execute the Second Amendment to the Professional Services Agreement with GHD, Inc., expanding the scope of work and increasing the contract amount by $78,164, for a new not-to-exceed amount of $808,134.

 

Strategic Plan:

 

N/A

 

 

Racial Equity:

 

Was this item identified as an opportunity to apply the Racial Equity Toolkit?

No

 

 

Prior Board Actions:

05/24/2022 Board approved the First Amendment to the Agreement for Engineering Services for Design of Leachate and Potable Water Storage Tanks Replacement Project with GHD, Inc.

07/20/2021 Board approved the Agreement for Engineering Services for Design of Leachate and Potable Water Storage Tanks Replacement Project with GHD, Inc.

 

 

Fiscal Summary

 Expenditures

FY24-25 Adopted

FY25-26 Projected

FY26-27 Projected

Budgeted Expenses

 

$78,164

 

Additional Appropriation Requested

 

 

 

Total Expenditures

 

$78,164

 

Funding Sources

 

 

 

General Fund/WA GF

 

 

 

State/Federal

 

 

 

Fees/Other

 

$78,164

 

Use of Fund Balance

 

 

 

General Fund Contingencies

 

 

 

Total Sources

 

$78,164

 

 

Narrative Explanation of Fiscal Impacts:

Costs associated with the additional work to be completed with the Second Amendment are estimated at $78,164; increasing the total not-to-exceed amount from $729,970 to $808,134. The $78,164 in additional expenses will be funded from Former Rural Landfill Fund 41122 and the Former Urban Landfill Fund 41123. Appropriations are available in the Fiscal Year 2025-26 Integrated Waste Adopted Budget for this work. Although costs associated to this proposed Second Amendment were unknown at the time of submittal of the FY 2025 -26 Recommended Integrated Waste Budget, some portions of closed landfill maintenance projects, such as road improvements at the closed landfills, can be deferred to the following Fiscal Year if needed.

Funding sources for maintaining the county closed landfills include collection of Franchise Fees under two Franchise Agreements and the collection of Concession Fees collected under a Master Operations Agreement with Republic Services of Sonoma County, Inc.

 

Narrative Explanation of Staffing Impacts (If Required):

None.

 

Attachments:

2nd Amendment

Exhibit A-2 Scope of Work

Exhibit B-2 Cost of Services

Exhibit C-1 Schedule of Rates

 

Related Items “On File” with the Clerk of the Board:

GHD Agreement

1st Amendment to the GHD Agreement

GHD 1st Term Extension