Skip to main content
File #: 2019-1032   
Type: Consent Calendar Item Status: Agenda Ready
File created: 7/9/2019 In control: General Services
On agenda: 7/9/2019 Final action:
Title: Sonoma Raceway Communication Tower & Vault Project Change Order and Budgetary Transfer
Department or Agency Name(s): General Services
Attachments: 1. Summary Report.pdf, 2. Att1-Budget Resolution.pdf

To: Sonoma County Board of Supervisors

Department or Agency Name(s): General Services

Staff Name and Phone Number: Mike Volatile, 707-565-1957                     

Vote Requirement: 4/5th

Supervisorial District(s): All

 

Title:

Title

Sonoma Raceway Communication Tower & Vault Project Change Order and Budgetary Transfer

End

 

Recommended Action:

Recommended action

A)                     Approve a $128,000 increase in the awarded Sonoma Raceway Communication Tower and Vault project construction contract with Alta Engineering for change orders as a result of underground conditions not covered in project plans and the awarded contract. (4/5th vote)

B)                     Approve the revised plans and specifications for the revised Sonoma Raceway Communication Tower and Vault project.

C)                     Approve an increase of $164,070 in the total project budget as a result of increases in the construction contract total, restoration of contingencies, and increased project costs.

D)                     Adopt a resolution authorizing budgetary adjustment and transfer of $164,070 from other completed General Fund projects in order to complete the Sonoma Raceway Communication Tower and Vault project. (4/5th vote)

 

end

 

Executive Summary:

The Board of Supervisors approved the Radio Infrastructure Communications Improvement program in 2012 as part of a broad effort to strengthen the interoperability of public safety communications in the Bay Area. The Sonoma Raceway Communication Tower and Vault Project was funded in the FY 2017-18 Capital Budget and approved to go to bid by the Board of Supervisors on May 8, 2018. The project was originally bid in June 2018, however, extenuating circumstances including an over-budget bid, bid protest, and potential impacts to native species, caused cancellation of the contract award. In response, the project scope was modified.  The project was then rebid in October 2018 and Alta Engineering Group was the lowest responsible bidder for the project at $882,540.  The contract was awarded by the Board on December 11, 2018.  Notice to proceed was given May 1, 2019 and is scheduled for completion in October 2019.

 

The original total project budget was estimated at $1,309,879. However, existing underground water lines in the project area have now been discovered, and relocating those facilities will require additional work and funding. Construction costs for such work are estimated at $128,000 and a total of $164,070 is needed to complete the extra work, increasing total project costs to $1,473,949.  Staff is proposing a budget transfer of available funds from completed projects in the amount of $164,070 in order to complete the project.    

 

Discussion:

Background

The County of Sonoma maintains a network of wireless communication facilities that provides voice radio and wireless data communication for essential services, including the 911 dispatch system, emergency fire services, emergency medical response services, law enforcement and other first responders, public safety and public works agencies. The Sonoma Raceway Tower and Vault will augment services for the southern areas of the County. The General Services Department manages the construction and maintenance of communication tower assets and is responsible for negotiating licenses or leases associated with equipment located on the towers. The department works with Federal, State, County law, fire, EMS and special districts and commercial entities to ensure the radio and wireless communication network serves the needs of the public.

 

Radio Infrastructure Program Funding

Radio Infrastructure improvement project priorities are established in the CIP and funding is based on the Board-adopted annual Capital Budget.  From FY 2006-07 to FY 2018-19, a total of $8.7 million has been budgeted for Radio Infrastructure improvement projects, and $6.8 million has been spent to-date.  Completed projects include towers and related supporting infrastructure and equipment at Mt. Jackson, Siri, Meyers Grade, Moonraker and Sonoma Raceway (formerly known as Sears Point Raceway and Infineon Raceway).  Historically, the General Fund has been the primary source of funding for the Radio Infrastructure program, although there was a contribution of $1,650,000 in Tobacco Securitization allocated in FY 2011-12.

 

Project Description

The scope of the Sonoma Raceway project is to erect an 80' self-supporting communications tower with all County-required antennas, supports, and cabling which will terminate in a new 18' X 25' pre-engineered metal communications equipment vault. The project includes all necessary site access, screen landscaping, electrical power and emergency generator support as required. The project site is located on lands owned by the Sonoma Raceway. This new facility will be a part of the essential services network supported for improved public safety. The Sheriff's Telecommunications Bureau has reviewed the specifications and found them satisfactory to meet their needs.

 

Funding

The Sonoma Raceway Tower project was established in the FY 2011-12 Capital Budget as part of the overall $1.4 million Radio Infrastructure Various Communication Towers program.  Initially $35,250 was allocated to start the Sonoma Raceway Tower design in FY 2011-12.  The Sonoma Raceway Tower project progressed through CEQA and design phases, utilizing additional approved funding of $204,874 allocated in FY 2012-13.  The Radio Infrastructure program funding was reassigned through Board approved Capital Budgets in FY 2014-15 and FY 2015-16 to other priority communications projects, resulting in a decrease of $130,177 to the Sonoma Raceway Tower original budget. In FY 2017-18 the construction phase of the Sonoma Raceway Tower was prioritized for funding by the Board during the Capital Budget process and subsequently received a $1.2 million General Fund allocation.  The budget description below includes the multi-year work on the project. The total project budget was originally $1,309,879. The increase ($164,070) proposed today will result in a revised budget total of $1,473,949.  Costs are allocated into the following budget categories:

 

 

Original Budget

Changes

Revised Budget

Construction

$882,540

$128,000

$934,290

Architect/Engineering

$135,740

0

$135,740

Other Consultants

$49,058

0

$49,058

Permits/Fees

$25,000

$6,500

$35,000

Project Management

$120,000

$29,570

$150,000

Special Inspections

$45,000

$0

$82,320

Project Contingency

$52,541

$0

$87,541

Total Project Cost

$1,309,879

$164,070

$1,473,949

 

The County General Services Department uses several different methodologies to develop project budget cost estimates. In the case of communications towers the FY 2018-19 Sonoma Raceway Tower construction budget estimate was based upon our prior experience constructing four communications sites (Mt. Jackson, Siri, Meyers Grade, and Moonraker), all of which were completed on time and under budget.  The cost of the contract with Alta Engineering for the Sonoma Raceway Tower was within the original project budget with funding already appropriated.

 

Need for Change Order

Since the contract was awarded and work began, project excavations at the site revealed the existence of underground water lines in critical project areas. The water lines are integral to the Sonoma Raceway’s onsite water treatment system and need to be relocated away from the project area. The lines should have been detected through standard due diligence by the County’s design consultant for the project, and the failure to account for these lines is a separate matter being separately pursued by the Department as appropriate. The relocation work nonetheless is needed in order to proceed with the project, and that work is estimated at $128,000.  Because the work involves further excavation and activity in the project area in conjunction with other construction activities being performed by Alta Engineering and the relocation work is urgently needed for the rest of the project to proceed, it is most efficient and in the County’s best interest for Alta Engineering to perform the relocation work.

 

 

Prior Board Actions:

12/11/2018 - Award of contract to Alta Engineering Group for construction of Sonoma Raceway Communication Tower and Vault

6/14/2018 - Adoption of FY 2018-19 Capital Budget

5/8/2018 - Approval of construction plans and specifications and contracting documents.  Approval of CEQA Notice of Exemption.

12/11/2012 - Authorization to hire Stantec for design consulting services

6/25/2012 - Adoption of FY 2011-12 Capital Budget with Communications Program

5/15/2011 - Accept report on FY 2012-2017 County of Sonoma Capital Project Plan

 

 

Fiscal Summary

 Expenditures

FY 19-20 Adopted

FY20-21 Projected

FY 21-22 Projected

Budgeted Expenses

$1,072,126

 

 

Additional Appropriation Requested

$164,070

 

 

Total Expenditures

$1,236,196

 

 

Funding Sources

 

 

 

General Fund/WA GF

$1,236,196

 

 

State/Federal

 

 

 

Fees/Other

 

 

 

Use of Fund Balance

 

 

 

Contingencies

 

 

 

Total Sources

$1,236,196

 

 

 

Narrative Explanation of Fiscal Impacts:

The original project budget for the Sonoma Raceway Tower is $1,309,879. Of that amount, $237,753 was spent in Fiscal Years 2011-12 and 2017-18. The balance remaining of $1,072,126 was included in the FY 2017-18 Communications Towers Capital Project budget.  Additional appropriations are needed in the amount of $164,070 to complete the work.  General Services proposes to reallocate remaining balances from completed capital projects to provide the General Fund sources necessary to cover the change order.  Funds available will come from the following completed [include date completed below] capital projects:

                     Paulin Well Relocation - $11,039

                     Car Wash Water Supply Relocation - $95,966

                     Fleet After Hours Key Kiosk Relocation - $12,719

                     Parking Improvements P26 Scoping - $44,346

 

 

Staffing Impacts:

 

 

 

Position Title (Payroll Classification)

Monthly Salary Range (A-I Step)

Additions (Number)

Deletions (Number)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Narrative Explanation of Staffing Impacts (If Required):

None

 

Attachments:

Attachment 1 - Budget Resolution

 

Related Items “On File” with the Clerk of the Board:

On File 1 - Drawings