File #: 2026-0266   
Type: Consent Calendar Item Status: Agenda Ready
File created: 2/18/2026 In control: Public Infrastructure
On agenda: 4/14/2026 Final action:
Title: Award the construction contract for the Watmaugh Road Bridge Replacement at Sonoma Creek (County Project Number C08001) and authorize a Performance Security Deposit with the California Department of Fish and Wildlife.
Department or Agency Name(s): Public Infrastructure
Attachments: 1. Summary Report, 2. Watmaugh Roadway Plans, 3. Watmaugh Bridge Plans, 4. Watmaugh Combined Cost Estimate, 5. Watmaugh Rd Bridge ITP

To: Board of Supervisors

Department or Agency Name(s): Sonoma County Public Infrastructure

Staff Name and Phone Number: Johannes J. Hoevertsz, 707-565-2550

Vote Requirement: Majority

Supervisorial District(s): First

 

Title:

Title

Award the construction contract for the Watmaugh Road Bridge Replacement at Sonoma Creek (County Project Number C08001) and authorize a Performance Security Deposit with the California Department of Fish and Wildlife.

End

 

Recommended Action:

Recommended action

A)                     Approve the plans and specifications for the Watmaugh Road Bridge Replacement at Sonoma Creek (County Project Number C08001).

B)                     Award the construction contract to the lowest responsible and responsive bidder Viking Construction Company, Inc., in the amount of $7,112,953.00.

C)                     Authorize a 20% contingency in the amount of $1,422,590.60, for a total contract not-to-exceed amount of $8,535,543.60.

D)                     Authorize the Director of the Department of Public Infrastructure to execute construction contract C08001.

E)                     Authorize the Director of the Department of Public Infrastructure to make all monetary deposits and pledges and take all other similar actions necessary to satisfy and comply with the performance security deposit requirement under the County’s Incidental Take Permit from the California Department of Fish and Wildlife for the Watmaugh Road Bridge Replacement Project.

F)                     Authorize the Auditor Controller Treasurer Tax Collector to execute all required financial documents associated with a letter of credit and other instruments as may be used as security for the Incidental Take Permit with the California Department of Fish and Wildlife.

end

 

Executive Summary:

Sonoma County Public Infrastructure (SPI) is requesting that the Board approve the plans and specifications and execute a construction contract with Viking Construction Company, Inc. for the Watmaugh Road Bridge Replacement at Sonoma Creek. If approved, the total, not to exceed value of the construction contract will be $7,112,953.00, plus authorization to the SPI for a 20% contingency.

Expenses associated with this contract are 88.53% reimbursable through the Federal Highway Bridge Program (HBP), with $9,802,000 in funding programmed by Caltrans for Fiscal Year 25/26. The County is responsible for the remaining 11.47% local match ($1,124,289) of which $50,529 is funded through the Local Bridge Seismic Retrofit Program. This project this subject to an Incidental Take Permit (ITP) issued by the California Department of Fish and Wildlife (CDFW), which requires implementation of habitat restoration and mitigation measures. In order to secure the County’s faithful performance of the work, the ITP requires CDFW receive a Letter of Credit as Security in the amount of $279,920.

 

Discussion:

The Watmaugh Road Bridge Replacement at Sonoma Creek Project (“Project”) will result in the construction of a new two-lane bridge to replace the existing, but functionally obsolete two-lane bridge. The new bridge is designed to meet current design standards including improvements to roadway approaches and appurtenant facilities. The project does not increase vehicular traffic capacity; however, it will provide two traffic lanes with shoulders as required by applicable standards. As part of this Project, the existing bridge will be removed before construction of the new bridge.

On July 31, 2012, following a competitive selection process, the Board approved an engineering and design contract for the Project with Moffatt and Nichol Engineers for a total not-to-exceed amount of $500,009 with a term ending December 31, 2015. The Board has approved several amendments to this design contract, most recently on April 18, 2023, when the Board approved a fourth amendment increasing the total not-to-exceed amount of the contract to $1,165,309 and extending the contract end date to December 31, 2026.

The Engineer’s Estimate for the Project was $8,868,677.22 and the Project was advertised for bids from February 10, 2026 to March 11, 2026. Bids were opened March 11, 2026, and were received as follows:

1.                     Viking Construction - $7,112,953.00

2.                     Disney Construction - $7,489,038.00

3.                     Gordon N. Ball - $7,643,471.50

4.                     Granite Construction - $8,437,748.38

5.                     Golden State Bridge, Inc - $9,416,104.52

6.                     Ghilotti Construction Co. - $9,525,527.50

7.                     Myers and Sons Construction - $9,580,654.10

The lowest responsive bid of $7,112,953.00 was approximately 22.4% lower than the Engineer’s Estimate, and in accordance with Public Contract Code Section 20128, the contract will be awarded to the lowest responsible and responsive bidder, which is Viking Construction Company, Inc.  If approved, the total, not to exceed value of the construction contract will be $8,535,543.60 including a 20% contingency.

Expenses associated with this contract are 88.53% reimbursable through the Federal Highway Bridge Program (HBP), with $9,802,000 in funding programmed by Caltrans for Fiscal Year 25/26. The County is responsible for the remaining 11.47% local match ($1,124,289) of which $50,529 is funded through the Local Bridge Seismic Retrofit Program.

On December 11, 2012, by Resolution No. 12-0586, the Board adopted a resolution certifying the Final Environmental Impact Report for the Project and, by Resolution No. 12-0587, adopted a statement of overriding conditions and a mitigation monitoring program and approved the Project. 

As part of the Environmental Permits associated with this project, the County has received an Incidental Take Permit from the California Department of Wildlife. Included in the conditions of the permit are stipulated mitigations activities. The estimated cost of these mitigations is listed in the permit, and comprise of four components: $79,920 for Habitat Creation for Freshwater Shrimp, $80,000 for Restoration of Habitat for Freshwater Shrimp, $80,000 for long-term management, $40,000 for associated professional costs. The total cost is estimated at $279,920. These costs have been included in the construction contract. CDFW requires a Performance Security for the entire estimated cost of the mitigation activities issued to CDFW in the form of an irrevocable letter of credit. This security must be in place prior to construction activities. The security will be released upon completion of mitigation activities.

 

 

Strategic Plan:

 

This item directly supports the County’s Five-year Strategic Plan and is aligned with the following pillar, goal, and objective.

 

Pillar: Resilient Infrastructure

Goal: Goal 3: Continue to invest in critical road, bridge, bicycle, and pedestrian infrastructure.

Objective: Objective 4: Identify and retrofit bridges in County that are at high risk for damage during earthquakes.

 

 

Racial Equity:

 

Was this item identified as an opportunity to apply the Racial Equity Toolkit?

No

 

 

Prior Board Actions:

4/18/2023 - Item 37: Fourth Amendment to the Contract with Moffatt and Nichol Engineers for design of the Watmaugh Bridge over Sonoma Creek Replacement Project.

12/4/2018 - Item 19: Second Amendment to the Agreement with Moffatt and Nichol Engineers for the design of the Watmaugh Bridge over Sonoma Creek Replacement Project.

5/12/2015 - Item 25: First Amendment to the Agreement with Moffatt and Nichol Engineers for the design of the Watmaugh Bridge over Sonoma Creek Replacement Project.

12/11/2012 - Certification of Final Environmental Impact Report and Approval of Project. 

7/31/2012 - Item 63: Professional Services Agreement for the design of the Watmaugh Bridge over Sonoma Creek Replacement Project awarded to Moffatt and Nichol Engineers.

 

 

Fiscal Summary

 Expenditures

FY25-26 Adopted

FY26-27 Projected

FY27-28 Projected

Budgeted Expenses

 

$8,535,543.60

 

Additional Appropriation Requested

 

 

 

Total Expenditures

 

$8,535,543.60

 

Funding Sources

 

 

 

General Fund/WA GF

 

 

 

State/Federal (FHWA, LBSRP)

 

$7,607,045.74

 

Fees/Other (SB1)

 

$928,497.86

 

Use of Fund Balance

 

 

 

General Fund Contingencies

 

 

 

Total Sources

 

$8,535,543.60

 

 

Narrative Explanation of Fiscal Impacts:

If awarded, the total value of the construction contract is $8,535,543.60 inclusive of a 20% contingency. Appropriations for this project will be included in the FY 2026-27 Roads Capital (11051-34010103) Recommended Budget. Expenses associated with this contract are 88.53% reimbursable through the Federal Highway Bridge Program (HBP), with $9,802,000 in funding programmed by Caltrans for Fiscal Year 25/26. The Roads Division is responsible for the remaining 11.47% local match of which $50,529 is funded through the Local Bridge Seismic Retrofit Program, with the balance covered by the Senate Bill 1 Road Maintenance and Rehabilitation Program (SB1).

 

Narrative Explanation of Staffing Impacts (If Required):

None.

 

Attachments:

100% Roadway Plans

100% Bridge Plans

100% Project Estimate

Incidental Take Permit (ITP)

 

Related Items “On File” with the Clerk of the Board:

Original Design Agreement

First Amendment to design Agreement

Second Amendment to design Agreement

Third Amendment to design Agreement

Fourth Amendment to design Agreement