File #: 2019-1342   
Type: Consent Calendar Item Status: Passed
File created: 8/23/2019 In control: Transportation and Public Works
On agenda: 9/17/2019 Final action: 9/17/2019
Title: Award of Contract for Old Monte Rio Road Slide Repair (Project C21601)
Department or Agency Name(s): Transportation and Public Works
Attachments: 1. Summary Report

To: Board of Supervisors

Department or Agency Name(s): Transportation and Public Works

Staff Name and Phone Number: Johannes J. Hoevertsz 707-565-2231

Vote Requirement: Majority

Supervisorial District(s): Fifth

 

Title:

Title

Award of Contract for Old Monte Rio Road Slide Repair (Project C21601)

End

 

Recommended Action:

Recommended action

A)                     Approve plans and specifications for the Old Monte Rio Slide Repair C21601.

B)                     Award contract to lowest responsible bidder, REGE Construction Inc. in the amount of $667,311 and authorize Chair to execute construction contract C21601.

C)                     Approve a construction contingency for the project in the amount of $66,731 for a total contract not to exceed $734,042.

(Fifth District)

end

 

Executive Summary:

The Department of Transportation and Public Works (TPW) is recommending the approval of plans and specifications for the Old Monte Rio Slide Repair and associated award of contract in the amount of $667,311 to the lowest responsible bidder, REGE Construction, Inc. As part of this project, TPW is recommending a 10% construction contingency of $66,731 to account for unforeseen conditions or project items that cannot be predetermined prior to the start of the project, for a total cost of $734,042. Costs associated with the construction contract are eligible for reimbursement through the Federal Emergency Management Agency (FEMA) for 75% and the State of California Office of Emergency Services (CalOES) for 18.75% of the allowable construction costs.

 

Discussion:

Old Monte Rio Road was damaged by debris flow and a landslide directly related to the storms of February 2017. The road suffered an approximately 164 foot slip out. The repair will include improvements to the roadway through the installation of a retaining wall (soldier pile) and road repair. The replacement section of the road will comply with applicable roadway and drainage standards to accommodate future storm events.

A Request for Bids along with associated advertising took place on August 1, 2019.

Bids were opened on August 22, 2019

Base bids were received and deemed responsive as follows:

1.                     REGE Construction Inc.                                          $667,311

2.                     Hillside Drilling Inc.                                          $698,369

3.                     Piazza Construction                                          $747,128

4.                     Maggiora & Ghillotti                                          $783,783

5.                     Valentine Corporation                                          $877,369

6.                     Ghillotti Construction                                          $910,185

7.                     Team Ghillotti                                          $931,417.7

8.                     Gordon N Ball Inc.                                          $975,985

The Engineer's Estimate was $771,934.00.

In accordance with Public Contract Code Section 20128, the contract shall be awarded to the lowest responsible bidder. TPW recommends awarding the contract to REGE Construction Inc., who was determined to be the lowest responsible bidder for this project.

The total estimated cost of construction is $734,042 which includes 10% for construction contingency. Appropriations are available in the FY 2019-20 Roads Capital Improvement budget. REGE Construction Inc., is experienced in this type of work.

 

Prior Board Actions:

None

 

Fiscal Summary

 Expenditures

FY 19-20 Adopted

FY20-21 Projected

FY 21-22 Projected

Budgeted Expenses

$734,042

 

 

Additional Appropriation Requested

 

 

 

Total Expenditures

$734,042

 

 

Funding Sources

 

 

 

General Fund/WA GF

 

 

 

State/Federal

$688,164

 

 

Fees/Other

 

 

 

Use of Fund Balance

$45,878

 

 

Contingencies

 

 

 

Total Sources

$734,042

 

 

 

Narrative Explanation of Fiscal Impacts:

Project costs were included in the FY 2019-20 Adopted Roads Division Capital Improvement Budget to be reimbursed with federal funds from FEMA at 75% and 18.75% from CalOES of the original estimate of $734,042including a 10% contingency. Remaining costs, estimated at $45,878, will be paid with available Roads fund balance budget designated for capital projects.

 

Staffing Impacts:

 

 

 

Position Title (Payroll Classification)

Monthly Salary Range (A-I Step)

Additions (Number)

Deletions (Number)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Narrative Explanation of Staffing Impacts (If Required):

None.

 

Attachments:

None.

 

Related Items “On File” with the Clerk of the Board:

Special Provisions; Bid Book; Addendum 1