Skip to main content
File #: 2024-0472   
Type: Consent Calendar Item Status: Agenda Ready
File created: 4/8/2024 In control: Public Infrastructure
On agenda: 5/21/2024 Final action:
Title: Award of Contract for Runway 14-32 Repairs - Charles M. Schulz - Sonoma County Airport
Department or Agency Name(s): Public Infrastructure
Attachments: 1. Summary Report, 2. Budgetary Resolution, 3. STS Rwy Storm Drain Repair_Bid Set Specs, 4. DRAFT Agreement

To: Board of Supervisors

Department or Agency Name(s): Sonoma County Public Infrastructure - Airport Division

Staff Name and Phone Number: Johannes J. Hoevertsz, 707-565-2550

Vote Requirement: 4/5th

Supervisorial District(s): Countywide

 

Title:

Title

Award of Contract for Runway 14-32 Repairs - Charles M. Schulz - Sonoma County Airport

End

 

Recommended Action:

Recommended action

A)                     Approve plans and specifications for the Charles M. Schulz - Sonoma County Airport Runway 14-32 Repair Project.

B)                     Award contract to the lowest responsive and responsible bidder, Granite Construction in the amount of $580,115.00.

C)                     Delegate authority to the Sonoma County Public Infrastructure (SPI) Director to execute the Construction Contract.

D)                     Delegate authority to the SPI Director to approve contingency for the project up to 15% in the amount of $87,000.00, for a total contract not to exceed amount of $667,115.00.

E)                     Adopt a budget resolution authorizing a budget adjustment to the FY 2023-2024 Final Budget for the Public Infrastructure Department in the amount of $667,115.00.

(4/5 vote required)

end

 

Executive Summary:

The Department of Public Infrastructure (SPI), Airport Division (Airport) is requesting the approval of the plans and specifications for the Charles M. Schulz - Sonoma County Airport Runway 14-32 repair project, award of a construction contract to the lowest responsive and responsible bidder, and authorization for the Director of SPI to execute the construction contract. As part of this project, Airport staff is recommending a 15% construction contingency to account for any unforeseen circumstances that cannot be predetermined prior to the start of the project.

 

Discussion:

The Airport has been monitoring two areas of runway 14-32 for pavement deterioration and signs of culvert failure.  During this time, the Federal Aviation Administration (FAA) has inspected the associated areas and recommended monitoring requirements for the pavement sections.  In the Winter of 2023-24, the Airport and the FAA observed that the pavement in question had further deteriorated and determined that permanent repairs are required to ensure continued compliance with FAA safety and operating standards.  To meet these standards, the Airport is proposing the following repairs:

1.                     Reconstruction of a 24-inch culvert that crosses under runway 14-32 near the intersection of runway 2-20, and

2.                     Mill 4 inches of existing pavement and place new asphalt in an area of the runway where rainwater has been ponding. 

 

The proposed work is scheduled to start early June and it will require closure of the airport’s two runways. The airport has coordinated with the FAA and stakeholders to mitigate the impacts of the expected 18 hours of work. 

xxx

On December 6, 2022, the Board approved Task Order #1 with Mead & Hunt, Inc. for general, program, grant management, airport pavement maintenance and repair consulting, and design services for the Airport. Mead & Hunt has provided design and bid administration assistance for this Runway Repair Project.

The Runway 14-32 Repair Project was advertised for bidding on April 11, 2024. Bids were opened on April 25, 2024.

Two bids were received and one deemed responsive and another one non-responsive as follows:

Granite Construction in the amount of $580,115.

Ghilotti Construction was deemed not responsive.

 

In accordance with Public Contract Code Section 20128, the contract shall be awarded to the lowest responsible bidder. The low bidder for this work is Granite Construction. The Department recommends awarding the contract to Granite Construction.

Department staff recommend that the Board of Supervisors award and authorize the Public Infrastructure Director to execute the agreement with Granite Construction in the amount of $580,115, including the 15% contingency, to complete the Runway 14-32 Repair Project at the Charles M. Schulz-Sonoma County Airport.

 

Strategic Plan:

 

This item directly supports the County’s Five-year Strategic Plan and is aligned with the following pillar, goal, and objective.

 

Pillar: Resilient Infrastructure

Goal: Goal 3: Continue to invest in critical road, bridge, bicycle, and pedestrian infrastructure.

Objective: Objective 1: Continue to maintain road segments, including designated turnouts where feasible, increase efforts on vegetation removal and drainage features, and improve pavement conditions in neighborhoods.

 

 

Racial Equity:

 

Was this item identified as an opportunity to apply the Racial Equity Toolkit?

No

 

 

Prior Board Actions:

12/6/2022:  Board approved the Master Consulting Agreement for planning, engineering and architectural services and associated task orders with Mead & Hunt, Inc. for the Charles M. Schulz - Sonoma County Airport

 

 

Fiscal Summary

 Expenditures

FY23-24 Adopted

FY24-25 Projected

FY25-26 Projected

Budgeted Expenses

 

$667,115

 

Additional Appropriation Requested

 

 

 

Total Expenditures

 

$667,115

 

Funding Sources

 

 

 

General Fund/WA GF

 

 

 

State/Federal

 

 

 

Fees/Other

 

$667,115

 

Use of Fund Balance

 

 

 

General Fund Contingencies

 

 

 

Total Sources

 

$667,115

 

 

Narrative Explanation of Fiscal Impacts:

The Airport is submitting a corresponding Budget Resolution with this Board Item to increase FY2023-24 Airport Capital Improvement (41301-34030104) appropriations for this project. This work will be funded by Airport Fees including Rents, Concessions, and Charges for Service. 

 

 

Narrative Explanation of Staffing Impacts (If Required):

None.

 

Attachments:

Budgetary Resolution

Bid Book

Agreement with Granite Construction

 

Related Items “On File” with the Clerk of the Board:

None.